Building control applications

Book a site inspection

Site visits are carried out between 10:30am and 3pm, Monday to Friday.

Inspections are usually carried out at the following stages:

  • Foundations excavated; when the foundations have been dug and before they are concreted.
  • Damp proof course or tanking.
  • Oversite.
  • Drainage.
  • Floor joists or block and beam.
  • Steelwork.
  • Roof carcass.
  • Insulation
  • Completion* - We ask for 48 hours' notice to allow our surveyors time to review the relevant information before the site visit.

Book a site inspection

To book a site inspection, you will need:

  • The name and telephone number of the site contact.
  • The address of the site where you need the inspection.
  • Information about the type of inspection you need.
  • Your preferred inspection date(s).

Book a site inspection online

Building Control surveyors will only attend inspections if you've applied for building regulations through us and paid the relevant fees.

*If a completion inspection is requested between one and ten years after the last recorded inspection, there will be a charge of £132. We will not carry out a completion inspection after 10 years from the last recorded inspection.